Skip to main content

NYC DOB Local Law 11

FISP Extension Requests in NYC for Unsafe Facade Repairs That Need More Time

DOB gives owners 90 days to repair conditions reported as Unsafe. When the work is too big for that window, a FISP extension request filed in DOB NOW Safety keeps the building covered and keeps failure to correct penalties from starting. We are a licensed and insured NYC facade contractor who prepares the repair schedule, contract, and permits your inspector needs to file each extension on time.

Independent contractor. Not affiliated with the NYC Department of Buildings.

FISP extension request illustrationRepair timeline showing the first 90 days after an Unsafe report, a FISP1 extension adding up to 90 days, a FISP2 extension, and the Unsafe completion date, with a DOB NOW Safety extension request card and the 305 dollar extension of time fee.UNSAFE REPAIR CLOCKRepair Timeline With ExtensionsFirst 90 DaysFISP1 +90FISP2Day 0Day 90Day 180Unsafecompletion dateEach request filed before the last one endsDOB NOW SAFETYExtension RequestFORMFISP1AcceptedFiled by the inspector, signed by ownerEXTENSION OF TIME$305per requestSealed repair timetableNotarized owner letterNo gaps between requests

In Short

FISP Extensions at a Glance

What Is a FISP Extension Request?

A FISP extension request asks DOB for more time to finish repairing conditions that a facade report rated Unsafe. The first request is the FISP1 Initial Extension of Time, and every request after it is a FISP2. Both are tied to the accepted Unsafe report and are filed in DOB NOW Safety by the licensed inspector who handles the building’s filings.

An extension covers repair time only. DOB’s fee schedule lists no extension for filing the report itself, so a building that missed its filing window is treated as a late FISP filing instead.

Reviewed by Muhammad Ali, Facade Contractor

Licensed and insured Local Law 11 repair work across NYC

Two construction professionals in hard hats reviewing the repair timetable for a FISP extension request

When a FISP Extension of Time Makes Sense

Most Unsafe repairs can finish in 90 days. These are the jobs that usually cannot.

Repairs Too Large for 90 Days

Rebuilding a parapet, replacing terra cotta units, or resetting a run of steel lintels often takes more than one season.

Permits Still Under Review

When the repair needs a DOB work permit or landmark approval, the clock can run out before work is allowed to start.

Neighbor Access Not Yet Signed

Rigging over an adjoining roof needs the neighbor’s written consent, and that agreement can take weeks.

Cold Weather Limits

Mortar, patching, and sealant work have temperature limits, so winter can stretch a masonry schedule.

What DOB Requires in a FISP1 Initial Extension

The FISP1 form and the DOB NOW Safety manual list these items for the first request.

01

Estimated Repair Time Statement

A signed and sealed statement from a licensed engineer or architect giving the time the repairs need.

02

Repair Timetable

A schedule that shows each phase of work and when it ends.

03

Temporary Safety Measures

An assessment of the shed, fence, or other protection keeping the public safe in the meantime.

04

Protection Permits

Copies of the shed or fence permit for the site.

05

Scope of Work and Permit

A short description of the repairs, with the work permit attached when one is required.

06

Notarized Owner Letter

A letter signed by the owner stating the work will be finished within the timetable.

Listed on DOB’s FISP1 form and in the DOB NOW Safety manual.

How a FISP2 Additional Extension Is Different

A FISP2 is filed when the FISP1, or the last FISP2, is about to run out. It works like a progress report. DOB wants to see what changed since the last request, not only a new end date.

If no work was done in the last period, the request must say so. A FISP2 that shows steady progress is far easier to support than one that shows none.

What a FISP2 Includes

FISP Extension Rules That Catch Owners Off Guard

No Gaps Between Requests

Owners owe civil penalties for any period after the first 90 days that an accepted extension does not cover. A late request leaves a gap.

The Unsafe Completion Date Is a Hard Stop

DOB will not grant an extension past the completion date on the report. Moving that date takes a subsequent report.

Tied to the Latest Unsafe Report

Requests are filed in the cycle with the most recent accepted Unsafe report and must cite the initial Unsafe report number, such as TR6-123456-I1.

Protection Stays in Place

The shed or fence stays up until an amended Safe or SWARMP report is accepted or DOB approves a partial shed removal.

Rules from DOB’s Façade Compliance page.

From Unsafe Report to Approved Extension, Step by Step

1

Unsafe Report Accepted

The 90-day repair clock starts, and protection goes up right away.

2

Scope, Contract, and Permits

We price the repairs, the owner signs the contract, and any needed permits are filed in the first weeks.

3

FISP1 Before Day 90

Your inspector files the initial extension with the timetable and the owner’s notarized letter, and the $305 fee is paid.

4

FISP2 Before Each Extension Ends

Progress photos, remaining work, and reasons for any delay go into the next request.

5

Repairs Finished

Your inspector files an amended report so the Unsafe status can close.

Start the FISP1 Early

A request filed weeks before day 90 leaves time to answer DOB questions. One filed on the last day risks a gap if DOB sends it back.

FISP Extensions vs Local Law 51 Shed Deadlines

Buildings whose first sidewalk shed permit was issued after Local Law 51 took effect face a second set of repair deadlines, with its own extension. The two are filed separately.

Detail FISP1 and FISP2 Local Law 51 Extension
What it extends
Time to repair Unsafe conditions after the 90-day window
Deadlines to file repair plans (5 months), file the permit application (8 months), and finish repairs (2 years) from the shed permit
What starts the clock
Filing of the Unsafe report
Issue date of the first sidewalk shed permit
Who requests it
The licensed inspector, after the owner signs
The owner, in writing
What it needs
Sealed time estimate, timetable, owner letter, permits
Documents explaining the delay and a contract with the scope and timeline
Penalty if missed
Failure to correct civil penalties for any uncovered period
$5,000 to $20,000 for each missed deadline
Fee
$305 per request
Set by DOB rule

From Local Law 51 and DOB’s Façade Fees and Penalties page. While a Local Law 51 request is pending, its deadlines are paused.

Mason setting a red brick in a mortar bed during Unsafe facade repairs

How Our Repair Team Backs Every FISP Extension Request

We do not file extensions. Your licensed inspector does, and we supply the construction records every request depends on.

1

A Signed Contract and Clear Scope

We price the Unsafe repairs and put the scope in writing, so the request has a real contract behind it.

2

A Timetable We Can Keep

We schedule each phase around permits, access, and weather, so the date your engineer seals is one we can meet.

3

Permits and Protection in Order

We file the work permits and keep the shed or fence permits current for every extension period.

4

Progress Photos Before Each FISP2

We send dated photos and work logs ahead of each deadline, so your inspector can file without chasing us.

Running Out of Repair Time?

Send the Unsafe report and the date it was accepted, and we will map out a repair schedule your inspector can file with.

What Adds Cost When FISP Repairs Run Long

Extra time has a price of its own, separate from the repairs. We quote the repair and protection work after a free review.

Penalty schedule from DOB’s FISP outreach presentation.

FISP Extension Terms on Your DOB Record

These three terms show up in DOB NOW Safety on a building with an open Unsafe report.

FISP1 Initial Extension of Time

The first request for more time to repair Unsafe conditions, filed after the Unsafe report is accepted.

FISP2 Additional Extension

Each later request, filed before the current extension ends and showing the work done since.

Unsafe Completion Date

The repair deadline set in the report. No extension can go past it.

FISP Extension Questions From NYC Owners

Not sure your repairs will finish on time? Call (917) 355-8556 or send us the report for a free extension review.

A FISP1 adds up to 90 days after the first 90-day repair window. After that, a FISP2 is filed before each extension ends, roughly every 90 days, until the work is done. No extension can go past the Unsafe completion date on the report.

DOB charges $305 for each extension of time to complete repairs. The inspector’s fee for preparing the request is separate, and so is the cost of keeping the shed or fence up longer.

The licensed inspector files it in DOB NOW Safety after the owner signs electronically. The owner also provides a notarized letter promising to finish the work within the timetable.

DOB’s fee schedule lists an extension only for completing repairs, not for filing the report. A building that missed its window should file as soon as possible to stop the late filing penalties.

The days between the two requests are not covered, and DOB can charge failure to correct penalties for that period. Filing the next request a few weeks early avoids the gap.

No. DOB will not grant time beyond the completion date listed in the report. Moving that date requires a subsequent report from the inspector.

No. The FISP1 and FISP2 forms apply to Unsafe conditions. SWARMP conditions carry their own repair date in the report, and any left unrepaired must be reported as Unsafe in the next cycle.

Not until the work is done and accepted. Protection stays up until an amended Safe or SWARMP report is accepted or DOB approves a partial shed removal.

Related Guides for Unsafe Facade Repairs

Each guide below covers a step that sits next to an extension request.